Fluren Projects

Glencore - Ulan Coal Mine Surface Operations

Upgrade of damaged steel pipe work with 400mm PN16 poly pipe, as part of an Underground Mine Water supply line. Sections were replaced down a steep rocky escarpment and required anchoring and restraining. Anchor blocks and clamps were designed and installed at the top of the escarpment to take the full weight of the pipeline once in an operational state. Fluren Project Managed the entire project - Cutting and Relocating of the poly pipe, Excavation and Concreting works, Polywelding and Multi Machine Operation of lowering the pipeline into its final position, bolting up to the existing lines and restraining to the anchor points.

Other Polywelding Projects

The
Latest

Glencore - Ulan Coal Mine Surface Operations

Upgrade of damaged steel pipe work with 400mm PN16 poly pipe, as part of an Underground Mine Water supply line. Sections were replaced down a steep rocky escarpment and required anchoring and restraining. Anchor blocks and clamps were designed and installed at the top of the escarpment to take the full weight of the pipeline once in an operational state. Fluren Project Managed the entire project - Cutting and Relocating of the poly pipe, Excavation and Concreting works, Polywelding and Multi Machine Operation of lowering the pipeline into its final position, bolting up to the existing lines and restraining to the anchor points.


Polywelding

Glencore - Ulan West LW6 Overland Pipeline

Installation of 3kms of 400mm poly pipeline for connection between existing infrastructure and three dewatering borehole pumps. Installed for the purpose of water extraction for ongoing underground mining operations. Project works included sourcing all poly pipe and parts, Welding of poly pipe onsite, Excavation works for burying pipeline, Trenching road crossings, Isolation of existing infrastructure for the purpose of safe connection and pressure testing of pipeline in accordance with Australian standards.


Polywelding

Glencore - Ulan West LW6 Borehole Connection

Connection of three dewatering boreholes to our previously installed 400mm overland poly pipeline. All poly pipework was fabricated at our workshop as per engineered designs and relocated to site for installation. Other project works included installation of various sized butterfly valves, pressure relief valves, flow metres, tapping saddle air relief valves, pressure gauges and ball valves in key points of the pipework. Also, a 22,500 litre poly overflow water tank was sourced with specific inlet and outlet fittings welded in to suit connection to our poly pipelines. The pipework was pressure tested to 1.5 times the operating pressure as per the Australian Standard before being handed over to the Client.


Polywelding

Glencore - Bulga Opencut Pit Services


Civil Services

Glencore - Bulga Underground Operations

Installation of Gas Pipeline used for extraction of underground gas for the production of long wall mining. Works include polypipe welding, excavation and installation, drill pad and road construction. Pipeline extraction and site rehabilitation after long wall completion.


Rehabilitation

Glencore - Bulga Opencut - Road Crossing


Civil Construction

Bloomfield - Rix's Creek Mine Rehabilitaion

Open-Cut Mine Rehabilitation consisting of spreading of bio solids, gypsum and fertiliser, seed re-contouring and shaping of overburden batters, installation of sediment and run off drains, installation of rock drop structures, spreading of top soil, ground preparation, rock raking, ripping and soil turning.


Rehabilitation

Glencore - Integra

Civil works and rehabilitation earthworks for gas wells and identified rehabilitation areas as part of the Integra Underground Operations (IUG) Closure Project 


Civil Services & Rehabilitation

Glencore - Ulan West LW8

Overland Pipeline

Supply & Install 8.5km overland pipeline and associated civil works.


Polywelding